Garage Building Site - Sept. 14, 2018
Garage Building Site with the topsoil scrapped off - Sept. 17, 2018
Garage Building Site, more equipment brought in, some fill in place - Sept. 18, 2018
Garage Building Site, more fill in place - Sept. 19, 2018
Garage Building Site, all the fill in place - Sept. 20, 2018
Garage Building Site, all site prep done, site graded and compacted - Sept. 26, 2018
Garage Building Site. Just waiting for the building permit to start! - Oct. 17, 2018
Garage Building Site, some material delivered, site set up to start work - Oct. 18, 2018
Garage Building Site, drilling post holes commences - Oct. 19, 2018
Garage Building Site, just 4 more holes to drill - Oct. 20, 2018
Garage Building Site, some posts set up - Oct. 23, 2018
Garage Building Construction, most of the poles are now set in - Oct. 24, 2018
Garage Building Construction, all of the poles are now set in - Oct. 25, 2018
Pouring the cement - 2018-10-26
Cement is poured, it's now Saturday, no more action until Monday (Weather permitting) - 2018-10-27
Truss headers are up, making progress - Oct. 29, 2018
Windows framed, garage door headers up - Nov. 01, 2018
More framing, weather prevented getting more done today - Nov. 01, 2018
Got some work done yesterday, today is Sunday, no working today, more tomorrow - Nov. 01, 2018
Trusses delivered, weather prevented getting any work done though - Nov. 06, 2018
Got a few of the lean-to trusses up today! More to come tomorrow - Nov. 08, 2018
The lean-to trusses are now up and the lean-to roof is sheeted - Nov. 09, 2018
6 Main Roof trusses are now up - Nov. 11, 2018
All the main roof trusses are now up - Nov. 12, 2018
Half the main roof sheeting is now on - Nov. 13, 2018
All the main roof sheeting is now on - Nov. 14, 2018
All roofing is now sheeted and dried in, now just waiting for the metal - Nov. 15, 2018
Sofit going on - Nov. 26, 2018
More sofit and perlins going on - Nov. 27, 2018
Nov. 29, 2018
Nov. 30, 2018
Man door and most windows are now in (gotta remember to lock that door at night) - Dec. 3, 2018
Sunny but cold, slow going - Dec. 4, 2018
Dec. 7, 2018
Dec. 11, 2018
Roof fascia on - Dec. 13, 2018
Large doors going on - Dec. 14, 2018
North side metal on - Dec. 17, 2018
All but the front side metal is on - Dec 18, 2018
All done! (except for the cement floor but that will wait until spring - Dec 21, 2018
More photo's of the finished building - Dec 22, 2018
More photo's of the finished building - Dec 22, 2018
More photo's of the finished building - Dec 22, 2018
More photo's of the finished building - Dec 22, 2018